Intelligent Scheduling for Underground Mobile Mining Equipment.

Song Z, Schunnesson H, Rinne M, Sturgul J - PLoS ONE (2015)

Bottom Line: This investigation first introduces the motivation, the technical background, and then the objective of the study.A decision support instrument (i.e. schedule optimizer for mobile mining equipment) is proposed and described to address this issue.The method and related algorithms which are used in this instrument are presented and discussed.

View Article: PubMed Central - PubMed

Affiliation: Department of Civil and Environmental Engineering, School of Engineering, Aalto University, Espoo, Finland.

ABSTRACT
Many studies have been carried out and many commercial software applications have been developed to improve the performances of surface mining operations, especially for the loader-trucks cycle of surface mining. However, there have been quite few studies aiming to improve the mining process of underground mines. In underground mines, mobile mining equipment is mostly scheduled instinctively, without theoretical support for these decisions. Furthermore, in case of unexpected events, it is hard for miners to rapidly find solutions to reschedule and to adapt the changes. This investigation first introduces the motivation, the technical background, and then the objective of the study. A decision support instrument (i.e. schedule optimizer for mobile mining equipment) is proposed and described to address this issue. The method and related algorithms which are used in this instrument are presented and discussed. The proposed method was tested by using a real case of Kittilä mine located in Finland. The result suggests that the proposed method can considerably improve the working efficiency and reduce the working time of the underground mine.

No MeSH data available.


Relations of the instrument and its environment.
© Copyright Policy
Related In: Results  -  Collection

License
getmorefigures.php?uid=PMC4476722&req=5

pone.0131003.g002: Relations of the instrument and its environment.

Mentions: The decision support instrument should be able to initiate schedules of mobile mining equipment for mine managers on a shift-to-shift basis, as well as propose solutions of new schedule when encountering unexpected events that can disturb underground mining. These events can consist of, but are not limited to: seismicity, rock failure, underground flood, shortage of power/air/water at working faces, breakdown of equipment (including mobile and immobile equipment), etc. Most control systems of immobile equipment (e.g. crushing, conveying, hoisting, and ventilation) have been configured according to their manufacturers specifications. These commercially available control systems are normally interfaced with computers and customized control loops. Since they are usually being configured at an optimum working condition during the commissioning of the equipment, it is not recommended to make changes or optimize during every shift. Therefore, the overall performance of mining process would be improved by optimizing the scheduling of the mobile mining equipment (e.g. drill rigs, shotcreters) by adapting the constraints of the above control systems and other underground conditions. Fig 2 gives the basic perspective of how the schedule optimizer interacts with its environment. The schedule optimizer will first gather the work plans from foremen, the availability of working faces, and the status and performance of equipment. Then it will schedule the mobile mining equipment. The scheduling aims to use the mobile mining equipment as optimally as possible to achieve the short-term mining plan as productive and energy-efficient as possible.


Intelligent Scheduling for Underground Mobile Mining Equipment.

Song Z, Schunnesson H, Rinne M, Sturgul J - PLoS ONE (2015)

Relations of the instrument and its environment.
© Copyright Policy
Related In: Results  -  Collection

License
Show All Figures
getmorefigures.php?uid=PMC4476722&req=5

pone.0131003.g002: Relations of the instrument and its environment.
Mentions: The decision support instrument should be able to initiate schedules of mobile mining equipment for mine managers on a shift-to-shift basis, as well as propose solutions of new schedule when encountering unexpected events that can disturb underground mining. These events can consist of, but are not limited to: seismicity, rock failure, underground flood, shortage of power/air/water at working faces, breakdown of equipment (including mobile and immobile equipment), etc. Most control systems of immobile equipment (e.g. crushing, conveying, hoisting, and ventilation) have been configured according to their manufacturers specifications. These commercially available control systems are normally interfaced with computers and customized control loops. Since they are usually being configured at an optimum working condition during the commissioning of the equipment, it is not recommended to make changes or optimize during every shift. Therefore, the overall performance of mining process would be improved by optimizing the scheduling of the mobile mining equipment (e.g. drill rigs, shotcreters) by adapting the constraints of the above control systems and other underground conditions. Fig 2 gives the basic perspective of how the schedule optimizer interacts with its environment. The schedule optimizer will first gather the work plans from foremen, the availability of working faces, and the status and performance of equipment. Then it will schedule the mobile mining equipment. The scheduling aims to use the mobile mining equipment as optimally as possible to achieve the short-term mining plan as productive and energy-efficient as possible.

Bottom Line: This investigation first introduces the motivation, the technical background, and then the objective of the study.A decision support instrument (i.e. schedule optimizer for mobile mining equipment) is proposed and described to address this issue.The method and related algorithms which are used in this instrument are presented and discussed.

View Article: PubMed Central - PubMed

Affiliation: Department of Civil and Environmental Engineering, School of Engineering, Aalto University, Espoo, Finland.

ABSTRACT
Many studies have been carried out and many commercial software applications have been developed to improve the performances of surface mining operations, especially for the loader-trucks cycle of surface mining. However, there have been quite few studies aiming to improve the mining process of underground mines. In underground mines, mobile mining equipment is mostly scheduled instinctively, without theoretical support for these decisions. Furthermore, in case of unexpected events, it is hard for miners to rapidly find solutions to reschedule and to adapt the changes. This investigation first introduces the motivation, the technical background, and then the objective of the study. A decision support instrument (i.e. schedule optimizer for mobile mining equipment) is proposed and described to address this issue. The method and related algorithms which are used in this instrument are presented and discussed. The proposed method was tested by using a real case of Kittilä mine located in Finland. The result suggests that the proposed method can considerably improve the working efficiency and reduce the working time of the underground mine.

No MeSH data available.